Has the Test Setup to be changed for some MRP Tests or does the ETS Board be enough?
Posted: 24 Nov 2025, 09:49
by Webinar_Question
Has the Test Setup to be changed for some MRP Tests or does the ETS Board be enough?
Re: Has the Test Setup to be changed for some MRP Tests or does the ETS Board be enough?
Posted: 26 Nov 2025, 13:33
by benja_m
Webinar_Question wrote: ↑24 Nov 2025, 09:49
Has the Test Setup to be changed for some MRP Tests or does the ETS Board be enough?
Some testcases require a different test setup than others. This is documented in Test specification.
In the certification tool, these testcases are bundled in separat folders. You will find
- ETS Test Setup (the default, connect dut to ETS board)
- ETS Test Setup extended for FSU (only for FSU tests, Scalance switch between dut and ETS board required)
- MRP Setup (only for some MRP tests, Siemens PLC needed in addition to dut and ETS)
In addition, the netload tests require another setup (not using ETS board at all).